2700 Bellevue Way SE
Data updated November 27, 2026, 4:50 PM PT
Under construction
About this project
At 2700 Bellevue Way SE in West Bellevue, Bellevue, the project rebuilt the South Bellevue Park and Ride as an elevated light rail station with a center platform, paired with a 5-level parking garage of 1,538 stalls and 436,315 square feet. The design review (14 134626 LD) covered about 2 miles of light rail facilities, the station, and a wetland mitigation site, and clearing and grading included excavation for the station and garage foundations and preparation of two mitigation areas.
Latest activity
Aug 16, 2021 update
The most recent permit on the record is a clearing and grading permit (19 123550 GD), closed in August 2021. The station permit (15 104488 BB) and the garage permit (15 107671 BB) both expired in May 2020, and no filings have followed the August 2021 closure.
Timeline
- ProposedJun 20, 2014
- Construction startedSep 22, 2016
Permits
Construction of 2 mi of light rail facilities includes one station S Bellevue and one wetland mitigation site.
Construction of a center platform elevated open light rail station at the existing S. Bellevue Park and Ride. Subsequent permits will be submitted for RoW use and improvements, clearing and grading of the site, a Utility Extension Agreement and a building permit for a 1538 stall, 5 level parking garage ajacent to the new station.
Clearing and grading activities associated with a new elevated light rail station and parking garage at the existing South Bellevue Park and Ride. This includes the demolition of existing utilities, landscaping, pavement and structures, civil work at the station site, excavation of foundations for the proposed elevated light rail station and five level parking garage, and site preparation for two mitigation areas., 15 104488 BB
This building permit is for the construction of the 5 level, 1,538 stall, 436,315 SF parking garage adjacent to the proposed South Bellevue Link Light Rail station (a part of the E320 contract). Construction would occur in conjunction with the light rail station development and require the closure of the existing S Bellevue Park and Ride for up to 5 years., 15 104488 BB
This permit application specifically addresses clearing and grading activities associated with a new elevated light rail station and parking garage at the existing South Bellevue Park and Ride. This includes the demolition of existing utilities, landscaping, pavement and structures, civil work at the station site, excavation of foundations for the proposed elevated light rail station and five
level parking garage, and site preparation for two mitigation areas., 15 104488 BB
Documents
Bellevue does not publish permit documents. Permit records are at
MyBuildingPermit.