About this project
At 1050 James St in Seattle's First Hill neighborhood, a 7-story structure with 75 apartment units and parking for 31 vehicles below grade was first filed in November 2014. Early design guidance proceeded under 3019219-EG, and the Master Use Permit (3019219-LU) was issued in August 2016. Construction was carried as a phased project (6504245-PH), with shoring and excavation under 6511705-CN.
Latest activity
Feb 5, 2018 update
The Certificate of Occupancy for the phased project (6504245-PH) was issued in February 2018, completing the project that month, following an earlier certificate in December 2017. The file holds 121 special-inspection reports, the most recent dated December 2017. Construction had begun in September 2016.
Timeline
- ProposedAug 31, 2015
- Construction startedSep 24, 2016
- CompletedFeb 5, 2018