First filed in May 2016, the development at 147 N 132nd St in Seattle's Broadview is a 3-story apartment building with 59 units and parking for 17 vehicles below grade, built after demolition of part of an existing structure. Early design guidance ran under 3024798-EG, and its Master Use Permit (3024798-LU) was issued in November 2017. A companion application (3025554-LU) adjusted the boundary between two parcels on the site.
Latest activity
Jun 5, 2019 update
The apartment building was completed on June 5, 2019, when its Certificate of Occupancy (6574965-CN) was issued, following a Temporary Certificate of Occupancy in March 2019. A companion permit (6607437-CN) covering alterations to the remaining portion of the existing church was completed in February 2019. The file holds 96 special-inspection reports, the most recent from February 2019.
Timeline
- ProposedOct 18, 2016
- Construction startedDec 5, 2017
- CompletedJun 5, 2019