A 24-story office tower paired with an 8-story building is proposed at 2230 7th Ave in Seattle's Denny Triangle, first filed in April 2015. The scheme in the Master Use Permit (3018578-LU) totals 853,049 square feet of office space and 23,128 square feet of retail, with parking for 877 vehicles below grade and demolition of the existing structures. An alley vacation was requested and granted for the development, and early design guidance was carried under 3018578-EG.

Latest activity

Jul 6, 2020 update

Initial tenant improvements to the ground level of the mixed use building (6752266-CN) were completed in June 2020, the newest dated item in the file. Shoring and excavation work (6582730-CN) was completed in March 2020, and 2 demolition permits (6582735-DM and 6582736-DM) closed in January 2019. The Master Use Permit (3018578-LU) itself is listed as Expired, and 2 later Master Use applications (3038079-LU and 3038080-LU) sit in Additional Info Requested status.

Timeline

Permits

3018578-EGEarly Design GuidanceCompleted
Early Design Guidance for: Land Use Application to allow a 24-story tower and an 8-story building containing 853,049 sq. ft. of office space and 23,128 sq. ft. of retail space. Parking for 877 vehicles to be provided below grade. Existing structures to be demolished. An alley vacation was requested and has been granted for this development. An addendum to the Downtown Height and Density EIS has been prepared.
3018578-LUMaster UseExpired
Land Use Application to allow a 24-story tower and an 8-story building containing 853,049 sq. ft. of office space and 23,128 sq. ft. of retail space. Parking for 877 vehicles to be provided below grade. Existing structures to be demolished. An alley vacation was requested and has been granted for this development. An addendum to the Downtown Height and Density EIS has been prepared.
3038079-LUMaster UseAdditional Info Requested
Western Neon has been working in the Seattle area since 1985 to build, service, and maintain the Emerald City's illuminated signs. We are currently helping refurbish the infamous Pink Elephant Car Wash sign while also celebrating the unsung female artist and designer who created it. A private donor is interested in installing an edition of this iconic sign at the Northeast corner of 7th Ave and Blanchard Street. To ensure this sculpture is viewed as a work of art, we are requesting a MUP Variance for this under Conditions 3 and 5 and then apply for a City of Seattle Sign Permit and proceed. That said, please see below for information on how we classify this unique object and how we would identify the artist on an informational plaque adjacent to the installation: Pink Elephant II The Pink Elephant II is a refurbished sculptural monument celebrating the original sign sited at the intersection of Denny and Dexter Avenues in proximity to Highway 99. It combines an original sign shell with new glass, electrical components, internal structure, and hardware while incorporating a decorative base reminiscent of the first Pink Elephant designed by artist Beatrice Haverfield. Neon and argon filled glass tubing, phosphorus powder, glass, aluminum, copper, patinated enamel over sheet metal, seven electromagnetic transformers, animator, GTO, carbon steel, stainless steel, hardware, 122" x 24" x 110", Seattle, 1956. About the Artist: Beatrice Haverfield Beatrice Haverfield (1913-1996) was an unparalleled artist, designer, and visionary who transformed the Seattle urban landscape. While her impact can be marked and remembered, her legacy is immeasurable. Beatrice was creative from an early age and honored her artistic talents while soaking up the rapidly changing Seattle skyline. From her first company with high school sweetheart Elden Fisler to her time with burgeoning company Campbell Neon, Beatrice was a unique and instrumental force. In her time, she created the infamous "Ivar's" sign on Pier 54, the futurist look of blue-collar mainstay "Chubby & Tubby's" as well as "The Dog House" and "Dick's Drive-In" and a multi-colored, show-stopping landmark for Cinerama. Never to rest on her laurels, Beatrice pulled out all the stops for her masterpiece, "The Pink Elephant." This one-of-a-kind monumental sculpture was more than a sign as it evoked an entire library of personal design moves. From characteristic script to industrial text, the "Pink Elephant" was a sublime mix of light, space, time, and commerce spinning above one of the busiest intersections in the city it symbolized - a city always on the way up, glittering against the ocean, mountains, and trees day and night. Please let me know if you have any questions and we look forward to working with you to establish the next steps as well as a realistic pre-construction, fabrication, and installation schedule based on a variance approval and permitting.
3038080-LUMaster UseAdditional Info Requested
Western Neon has been working in the Seattle area since 1985 to build, service, and maintain the Emerald City's illuminated signs. We are currently helping refurbish the infamous Pink Elephant Car Wash sign while also celebrating the unsung female artist and designer who created it. A private donor is interested in installing an edition of this iconic sign at the Northeast corner of 7th Ave and Blanchard Street. To ensure this sculpture is viewed as a work of art, we are requesting a MUP Variance for this under Conditions 3 and 5 and then apply for a City of Seattle Sign Permit and proceed. That said, please see below for information on how we classify this unique object and how we would identify the artist on an informational plaque adjacent to the installation: Pink Elephant II The Pink Elephant II is a refurbished sculptural monument celebrating the original sign sited at the intersection of Denny and Dexter Avenues in proximity to Highway 99. It combines an original sign shell with new glass, electrical components, internal structure, and hardware while incorporating a decorative base reminiscent of the first Pink Elephant designed by artist Beatrice Haverfield. Neon and argon filled glass tubing, phosphorus powder, glass, aluminum, copper, patinated enamel over sheet metal, seven electromagnetic transformers, animator, GTO, carbon steel, stainless steel, hardware, 122" x 24" x 110", Seattle, 1956. About the Artist: Beatrice Haverfield Beatrice Haverfield (1913-1996) was an unparalleled artist, designer, and visionary who transformed the Seattle urban landscape. While her impact can be marked and remembered, her legacy is immeasurable. Beatrice was creative from an early age and honored her artistic talents while soaking up the rapidly changing Seattle skyline. From her first company with high school sweetheart Elden Fisler to her time with burgeoning company Campbell Neon, Beatrice was a unique and instrumental force. In her time, she created the infamous "Ivar's" sign on Pier 54, the futurist look of blue-collar mainstay "Chubby & Tubby's" as well as "The Dog House" and "Dick's Drive-In" and a multi-colored, show-stopping landmark for Cinerama. Never to rest on her laurels, Beatrice pulled out all the stops for her masterpiece, "The Pink Elephant." This one-of-a-kind monumental sculpture was more than a sign as it evoked an entire library of personal design moves. From characteristic script to industrial text, the "Pink Elephant" was a sublime mix of light, space, time, and commerce spinning above one of the busiest intersections in the city it symbolized - a city always on the way up, glittering against the ocean, mountains, and trees day and night. Please let me know if you have any questions and we look forward to working with you to establish the next steps as well as a realistic pre-construction, fabrication, and installation schedule based on a variance approval and permitting.
6459134-DMDemolitionExpired
Demolition of existing 1-story vacant building per plan.
6459663-PHPhasedExpired
Phased project: Construction of office and retail buildings with shared below grade parking and occupy per plan
6582730-CNConstructionCompleted
Shoring and Excavation for construction of office and retail buildings with shared below grade parking per plan
6582735-DMDemolitionClosed
Demolish existing commercial building (existing asphalt to remain) per plans
6582736-DMDemolitionClosed
Demolish existing commercial building (existing asphalt to remain) per plans
6752266-CNConstructionCompleted
Initial tenant improvements to north portion of level G of mixed use building for retail per plan.

Documents

City documents for this project's records are filed at Seattle EDMS:
3018578-EG
3018578-LU
3038079-LU
3038080-LU
6459134-DM
6459663-PH
6582730-CN
6582735-DM
6582736-DM
6752266-CN