2525 Minor Ave E
Data updated November 27, 2026, 4:50 PM PT
Neighborhood: Eastlake
- City documents on file96
- Latest activityMay 15, 2024
About this project
The work at 2525 Minor Ave E in Seattle's Eastlake neighborhood adds homes inside an existing apartment building rather than replacing it; the project was first filed in June 2014. A land-use filing (3017820-LU) covering a tenant-improvement approach to adding 14 dwelling units within the building envelope was canceled. The additions proceeded in stages under construction permits: a cellar-level conversion of storage space into a dwelling unit, with carports enclosed (6474763-CN), and later alterations adding dwelling units at the basement level (6835290-CN). Voluntary seismic upgrades to the basement were permitted separately (6713116-CN).
Latest activity
May 15, 2024 update
A Certificate of Occupancy for the basement additions permit (6835290-CN) was issued in May 2024, and the project completed that month, after a Temporary Certificate of Occupancy in January 2024. The earlier cellar conversion (6474763-CN) had received its own Certificate of Occupancy in March 2020. The file holds 14 special-inspection reports, the most recent dated June 2020.
Timeline
- ProposedMay 2, 2022
- Construction startedMar 16, 2023
- CompletedMay 15, 2024