3220 Fuhrman Ave E

Data updated November 27, 2026, 4:50 PM PT

Withdrawn
Presentation slide 1
Presentation: Design Review Proposal, Oct 20, 2016. Source: Seattle city records.1 / 24

About this project

First filed in January 2011, the proposal at 3220 Fuhrman Ave E in Portage Bay, Seattle, is a 6-story apartment building with 8 units in an environmentally critical area, under a shoreline substantial development application. Parking for 4 vehicles sits inside the structure, and the existing building was to be demolished. An early version (3011981-LU) was canceled for no activity in January 2015, and the scheme was refiled and carried in a later Master Use record (3019308-LU).

Latest activity

May 16, 2019 update

The most recent filing at the site is a demolition permit (6615936-DM) from May 2019, which sits at awaiting information, seeking to demolish the existing triplex. The later Master Use record (3019308-LU) stands issued, but the construction record (6453734-CN) stands canceled, the last activity dates to May 2019, and the apartment building was not built.

Timeline

Permits

6453734-CNConstructionCanceled
Construct multi-family structure with parking garage occupy per plans. (Construct multi-family structure with parking garage including shoring on adjacent property. Review and process for 2 record #'s under 6453734-CN.)
6615936-DMDemolitionAwaiting Information
Demolish existing triplex per plan.
3011981-LUMaster UseCanceled
CANCELLED DUE TO NO ACTIVITY 1/29/15 MH - construciton of a six-story building with underground parking containing six dwelling units
3019308-LUMaster UseIssued
Shoreline Substantial Development Application to allow a six-story, eight-unit apartment building in an environmentally critical area. Parking for four vehicles will be provided within the structure. Existing building to be demolished.

Documents

60 documents tracked here, newest first, of 126 on file with the city.
May 16, 2019Record Snapshot
Record Snapshot · 6615936-DM · Demolition Permit
Apr 26, 2019Cover Sheet
Cover Sheet · 6615936-DM · Demolition Permit
Apr 26, 2019Cover Sheet
Cover Sheet · 6453734-CN · Construction Permit
Apr 5, 2019Inspection Schedule
Inspection Schedule · 6453734-CN · Upload Documents
Apr 5, 2019Inspection Schedule
Inspection Schedule · 6453734-CN · Upload Documents
Apr 5, 2019Inspection Schedule
Inspection Schedule · 6453734-CN · Upload Documents
Apr 5, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Apr 5, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Apr 2, 2019Memorandum of Drainage Control
Memorandum of Drainage Control · 6453734-CN · Construction Permit
Mar 13, 2019Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Mar 12, 2019Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Mar 2, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Mar 2, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Mar 2, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Mar 2, 2019Inspection Schedule
Inspection Schedule · 6453734-CN · Upload Documents
Mar 2, 2019Inspection Schedule
Inspection Schedule · 6453734-CN · Upload Documents
Mar 2, 2019Inspection Schedule
Inspection Schedule · 6453734-CN · Upload Documents
Mar 2, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Mar 2, 2019Geotechnical Engineer Statement
Geotechnical Engineer Statement · 6453734-CN · Upload Documents
Mar 2, 2019Side Yard Easement
Side Yard Easement · 6453734-CN · Upload Documents
Mar 2, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Mar 2, 2019Memorandum of Drainage Control
Memorandum of Drainage Control · 6453734-CN · Upload Documents
Mar 2, 2019Correction Response
Correction Response · 6453734-CN · Upload Documents
Nov 14, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Oct 30, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Oct 17, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Oct 9, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Oct 3, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Sep 26, 2018No Protest Agreement
No Protest Agreement · 6453734-CN · Upload Documents
Aug 17, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
Aug 17, 2018Inspection Schedule
Inspection Schedule · 6453734-CN · Upload Documents
Aug 17, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
Aug 17, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
Aug 17, 2018Drainage Report
Drainage Report · 6453734-CN · Upload Documents
Jun 19, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Jun 13, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Jun 7, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Jun 4, 2018Optional Applicant Upload
Optional Applicant Upload · 6453734-CN · Construction Permit
Jun 4, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
May 17, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
May 2, 2018Geotechnical Engineer Statement
Geotechnical Engineer Statement · 6453734-CN · Upload Documents
May 2, 2018Geotech Engineer's Letter of Evaluation
Geotech Engineer's Letter of Evaluation · 6453734-CN · Upload Documents
May 2, 2018Geotechnical Engineer Statement
Geotechnical Engineer Statement · 6453734-CN · Upload Documents
May 2, 2018Geotechnical Engineer Statement
Geotechnical Engineer Statement · 6453734-CN · Upload Documents
May 2, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
May 2, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
May 2, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
May 2, 2018Envelope Summary
Envelope Summary · 6453734-CN · Upload Documents
May 2, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
May 2, 2018Drainage Report
Drainage Report · 6453734-CN · Upload Documents
May 2, 2018Drainage Report
Drainage Report · 6453734-CN · Upload Documents
May 2, 2018Correction Response
Correction Response · 6453734-CN · Upload Documents
Apr 28, 2018Preliminary Assessment Report
Preliminary Assessment Report · 6453734-CN · Special Inspection
Apr 28, 2018Preliminary Assessment Report
Preliminary Assessment Report · 3011981-LU · Master Use Permit
Feb 1, 2018Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Dec 6, 2017Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Nov 30, 2017Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Nov 1, 2017Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Nov 1, 2017Correction Letter
Correction Letter · 6453734-CN · Construction Permit
Oct 30, 2017PUBLISHED Decision/Recommendation
PUBLISHED Decision/Recommendation · 6453734-CN · Construction Permit