3835 59th Ave SW
Data updated November 27, 2026, 4:50 PM PT
Neighborhood: West Seattle
Completed
- City documents on file85
- Latest activityMar 14, 2025
About this project
At 3835 59th Ave SW in Alki, Seattle, a rowhouse project was built under a single construction record, with no land-use filing in the packet. The record (6945664-CN) established the rowhouse use and covered construction of the new multifamily buildings.
Latest activity
Mar 14, 2025 update
The construction record (6945664-CN) was completed in March 2025, the project's completion date. Construction had begun in February 2024. The file holds 37 special-inspection reports, the most recent from February 2025.
Timeline
- ProposedJul 5, 2023
- Construction startedFeb 14, 2024
- CompletedMar 14, 2025
Permits
Establish use as rowhouses (4 total units) per land use code. Construct new multifamily buildings occupy per plan.
Documents
60 documents tracked here, newest first, of 85 on file with the city.
Mar 5, 2025Field Requested Supporting Document
Field Requested Supporting Document · 6945664-CN · Construction Permit
Mar 4, 2025Inspection Report
Inspection Report · 6945664-CN · Construction Permit
Feb 25, 2025Special Inspection Final Report
Special Inspection Final Report · 6945664-CN · Special Inspection
Feb 20, 2025Special Inspection Final Report
Special Inspection Final Report · 6945664-CN · Special Inspection
Feb 14, 2025Special Inspection Final Report
Special Inspection Final Report · 6945664-CN · Special Inspection
Jan 24, 2025Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jan 24, 2025Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jan 10, 2025Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jan 8, 2025Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jan 8, 2025Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jan 8, 2025Special Inspection Final Report
Special Inspection Final Report · 6945664-CN · Special Inspection
Jan 8, 2025Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jan 8, 2025Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jan 8, 2025Special Inspection Final Report
Special Inspection Final Report · 6945664-CN · Special Inspection
Aug 26, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jul 23, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jul 11, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jul 11, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jul 11, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jul 11, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jul 11, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jun 27, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jun 24, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Jun 4, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
May 29, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
May 29, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
May 23, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
May 23, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
May 3, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Apr 19, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Apr 16, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Apr 15, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Apr 15, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Apr 12, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Apr 10, 2024Special Inspection Field Report
Special Inspection Field Report · 6945664-CN · Special Inspection
Feb 14, 2024Approved Cover Sheet
Approved Cover Sheet · 6945664-CN · Construction Permit
Feb 14, 2024Permit
Permit · 6945664-CN · Construction Permit
Feb 14, 2024Record Snapshot
Record Snapshot · 6945664-CN · Construction Permit
Feb 13, 2024MHA-Payment Received
MHA-Payment Received · 6945664-CN · Construction Permit
Feb 8, 2024MHA-Commitment Letter
MHA-Commitment Letter · 6945664-CN · Construction Permit
Jan 24, 2024Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Jan 11, 2024Optional Applicant Upload
Optional Applicant Upload · 6945664-CN · Construction Permit
Jan 10, 2024Geotech Engineer's Letter of Evaluation
Geotech Engineer's Letter of Evaluation · 6945664-CN · Upload Documents
Dec 19, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Dec 18, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Dec 18, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Dec 15, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Dec 5, 2023Optional Applicant Upload
Optional Applicant Upload · 6945664-CN · Construction Permit
Dec 4, 2023Memorandum of Drainage Control
Memorandum of Drainage Control · 6945664-CN · Upload Documents
Dec 4, 2023Covenant for Owner Occupancy
Covenant for Owner Occupancy · 6945664-CN · Upload Documents
Dec 4, 2023Green Building Other
Green Building Other · 6945664-CN · Upload Documents
Dec 4, 2023Inspection Schedule
Inspection Schedule · 6945664-CN · Upload Documents
Dec 4, 2023Drainage Report
Drainage Report · 6945664-CN · Upload Documents
Nov 6, 2023Special Inspection Notification
Special Inspection Notification · 6945664-CN · Construction Permit
Nov 6, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Oct 19, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Oct 19, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Oct 19, 2023Correction Letter
Correction Letter · 6945664-CN · Construction Permit
Oct 10, 2023Recorded Side Sewer Release and Indemnification
Recorded Side Sewer Release and Indemnification · 6945664-CN · Construction Permit
Oct 10, 2023Covenant-Liquefaction Prone Area
Covenant-Liquefaction Prone Area · 6945664-CN · Construction Permit