About this project
The project at 5701 M L King Jr Way S in Seattle's Mid-Beacon Hill neighborhood, first filed in November 2013, centers on a 4-story apartment building with ground-floor commercial space and no basement, described in a Master Use filing (3012447-LU) that also covered demolition of the existing building. A companion application (3016146-LU) addressed the site's contaminated soil, proposing excavation of 400 cubic yards to be replaced with clean fill.
Latest activity
Apr 28, 2018 update
The grading permit (3016146-LU) was issued in January 2014, with a determination of non-significance prepared by Sound Transit. The apartment filing (3012447-LU) is closed, the last activity in the record is April 2018, and no construction permits are in the family.
Timeline
- ProposedNov 8, 2013