First filed in November 2009, the proposal at 7125 Fauntleroy Way SW in Gatewood, Seattle, centered on the Kenney retirement campus, with a contract rezone and a large expansion of its independent living, assisted living, and nursing home facilities under a Master Use application (3008453-LU). A later scheme (3026106-LU), with early design guidance (3026106-EG), narrowed the focus to a 42-unit apartment building for seniors over below-grade parking, plus 4 to 8 rowhouse units, south of the campus.

Latest activity

Apr 28, 2018 update

The campus expansion application (3008453-LU) was canceled in October 2013, as its description records, and the later senior housing applications (3026106-LU and 3029994-LU) were withdrawn. The newest documents are preliminary assessment reports from April 2018, and nothing was built under these records.

Timeline

Permits

3008453-EGEarly Design GuidanceCanceled
Early Design Guidance for: CANCELED 10/21/2013 Council Land Use Action to contract rezone 228,490 sq. ft. of land from LDT & L3 to MR and to allow a 387,450 sq. ft. expansion to an existing independent living apartment, assisted living and nursing home facility (The Kenney). Project includes three, 4-6 story multifamily structures containing 202 independent living apartments, 112 assisted living units, and 35 skilled nursing units. Parking for 279 vehicles to be provided below grade. Project includes 57,681 cu. yds. of grading and street vacation (46th Pl SW). Existing landmark building (Seaview) to be modified and relocated on site. Ten existing multifamily structures to be demolished. Council file #309618
3026106-EGEarly Design GuidanceClosed
Early Design Guidance for: Contract rezone of property to the south of the Kenney retirement campus from LR1 to LR3 to allow construction of a 40-42 unit apartment building for seniors over below grade parking and 4-8 row house units with attached parking.
3008453-LUMaster UseCanceled
CANCELED 10/21/2013 Council Land Use Action to contract rezone 228,490 sq. ft. of land from LDT & L3 to MR and to allow a 387,450 sq. ft. expansion to an existing independent living apartment, assisted living and nursing home facility (The Kenney). Project includes three, 4-6 story multifamily structures containing 202 independent living apartments, 112 assisted living units, and 35 skilled nursing units. Parking for 279 vehicles to be provided below grade. Project includes 57,681 cu. yds. of grading and street vacation (46th Pl SW). Existing landmark building (Seaview) to be modified and relocated on site. Ten existing multifamily structures to be demolished. Council file #309618
3026106-LUMaster UseWithdrawn
Contract rezone of property to the south of the Kenney retirement campus from LR1 to LR3 to allow construction of a 40-42 unit apartment building for seniors over below grade parking and 4-8 row house units with attached parking.
3029994-LUMaster UseWithdrawn

Documents

9 documents tracked here, newest first.
Apr 28, 2018Preliminary Assessment Report
Preliminary Assessment Report · 3026106-EG · Early Design Guidance
Apr 28, 2018Preliminary Assessment Report
Preliminary Assessment Report · 3008453-EG · Early Design Guidance
Dec 29, 2016Design Review Proposal
Design Review Proposal · 3008453-LU · Master Use Permit
Oct 21, 2016Site Photos
Site Photos · 3026106-LU · Master Use Permit
Oct 17, 2016Site Plan
Site Plan · 3026106-LU · Master Use Permit
Oct 7, 2016Legal Description
Legal Description · 3026106-LU · Master Use Permit
Nov 6, 2009Pre-Application Site Visit Request (PASV)
Pre-Application Site Visit Request (PASV) · 3008453-LU · Master Use Permit
Nov 6, 2009Site Photos
Site Photos · 3008453-LU · Master Use Permit
Nov 5, 2009Pre-Application Site Visit Request (PASV)
Pre-Application Site Visit Request (PASV) · 3008453-LU · Master Use Permit