Data updated November 27, 2026, 4:50 PM PT

Neighborhood: Rainier Valley

Completed
Presentation slide 1
Presentation: Design Review EDG Proposal - Final, Jun 9, 2020. Source: Seattle city records.1 / 60

About this project

At 7357 43rd Ave S in Brighton, Seattle, first filed in February 2019, a 7-story apartment building holds 104 units, with 2 live-work units and a community center, and no parking. Administrative design review was conducted under 3024248-EG, where the scheme was described at 100 units, before the Master Use Permit (3034491-LU) was issued in April 2020 at 104 units. Existing buildings on the site were demolished.

Latest activity

Sep 17, 2021 update

The project was completed in September 2021, when Certificates of Occupancy were issued for the building permit (6723755-CN), days after a Temporary Certificate of Occupancy. Construction had started in May 2020. The file holds 104 special-inspection reports, the most recent in August 2021.

Timeline

Permits

6723755-CNConstructionCompleted
Construct new mixed-use structure occupy per plan. Mechanical Included
3024248-EGEarly Design GuidanceCompleted
Administrative Design Review for a 7-story, 100-unit apartment building. No parking proposed. Existing buildings to be demolished.
3034491-LUMaster UseExpired
Land Use Application to allow a 7-story, 104-unit apartment building with 2 live-work units and community center. No parking proposed. Existing buildings to be demolished. Administrative Design Review conducted under 3024248-EG.

Documents

60 documents tracked here, newest first, of 299 on file with the city.
Sep 17, 2021Certificate of Occupancy
Certificate of Occupancy · 6723755-CN · Construction Permit
Sep 17, 2021Certificate of Occupancy
Certificate of Occupancy · 6723755-CN · Construction Permit
Sep 10, 2021Temporary Certificate of Occupancy
Temporary Certificate of Occupancy · 6723755-CN · Construction Permit
Aug 30, 2021Landscape Improvement Checklist
Landscape Improvement Checklist · 6723755-CN · Construction Permit
Aug 11, 2021Special Inspection Final Report
Special Inspection Final Report · 6723755-CN · Special Inspection
Jul 28, 2021Inspection Report
Inspection Report · 6723755-CN · Construction Permit
Jul 21, 2021Special Inspection Final Report
Special Inspection Final Report · 6723755-CN · Special Inspection
Jul 21, 2021Special Inspection Final Report
Special Inspection Final Report · 6723755-CN · Special Inspection
Jul 21, 2021Special Inspection Final Report
Special Inspection Final Report · 6723755-CN · Special Inspection
Jul 2, 2021Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
May 14, 2021Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Mar 17, 2021Correction Letter
Correction Letter · 6723755-CN · Shop Drawing
Mar 17, 2021Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Mar 15, 2021Approved Cover Sheet
Approved Cover Sheet · 6723755-CN · Construction Permit
Feb 18, 2021Permit
Permit · 6723755-CN · Construction Permit
Feb 18, 2021Approved Revised Plan Sheets
Approved Revised Plan Sheets · 6723755-CN · Revision Request - Building
Jan 27, 2021Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Jan 27, 2021Record Snapshot
Record Snapshot · 6723755-CN · Revision Request - Building
Jan 21, 2021Revision Letter
Revision Letter · 6723755-CN · Revision Request - Building
Jan 21, 2021Revision Letter
Revision Letter · 6723755-CN · Revision Request - Building
Jan 14, 2021Permit
Permit · 6723755-CN · Construction Permit
Jan 14, 2021Correction Response
Correction Response · 6723755-CN · Upload Documents
Jan 14, 2021Correction Response
Correction Response · 6723755-CN · Upload Documents
Jan 11, 2021Approved Revised Plan Sheets
Approved Revised Plan Sheets · 6723755-CN · Revision Request - Building
Jan 8, 2021Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Jan 8, 2021Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Jan 8, 2021Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Dec 30, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Dec 30, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Dec 30, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Dec 15, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Dec 2, 2020Record Snapshot
Record Snapshot · 6723755-CN · Revision Request - Building
Nov 25, 2020Revision Letter
Revision Letter · 6723755-CN · Revision Request - Building
Nov 25, 2020Revision Letter
Revision Letter · 6723755-CN · Revision Request - Building
Nov 23, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 23, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 18, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 18, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 18, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 12, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 12, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 12, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 12, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 6, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 6, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 6, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 6, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 6, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Nov 6, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 26, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 26, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 13, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 13, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 13, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 13, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 13, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 13, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 6, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 5, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection
Oct 5, 2020Special Inspection Field Report
Special Inspection Field Report · 6723755-CN · Special Inspection