851 12th Ave
Data updated November 27, 2026, 4:50 PM PT
Neighborhood: Downtown Seattle
- Stories5
- Latest activityMay 13, 2019
About this project
First filed in July 2018, the project at 851 12th Ave in First Hill, Seattle, is a 5 story institutional building, the Seattle University Center for Science and Innovation. Its Master Use Permit (3030809-LU) proposed no additional parking and called for an existing building to be demolished. The construction side was organized as a phased project covering the academic building and an accessory detached open roof portico, with mechanical work included.
Latest activity
May 13, 2019 update
The phased construction permit (6689849-PH) was issued in June 2019, days after its Master Use Permit (3030809-LU) was issued the same month, and both records are now Expired. No dated movement after June 2019 appears in the packet, so the under construction listing rests on that 2019 phased issuance rather than on any later filing.
Timeline
- ProposedJul 24, 2018
- Construction startedJun 17, 2019