About this project

The project at 938 10th Ave E in Seattle's Broadway neighborhood altered an existing apartment building, establishing multi-family use and adding a third story on top of it. The work was carried on a single construction record, 6444751-CN, applied for in December 2014. No land-use application or design review record accompanies it in the file, and the record gives no unit count for the enlarged building beyond its multi-family use.

Latest activity

Sep 2, 2016 update

A certificate of occupancy for 6444751-CN was issued in September 2016, the project's recorded completion date. The construction permit had been issued in August 2015. The file holds 11 special-inspection reports, all structural, with the most recent dated June 2016, a few months before occupancy was granted.

Timeline

Permits

6444751-CNConstructionCompleted
Establish multi-family use and construct alterations and 3rd story addition to an existing apartment building per plans.

Documents

53 documents tracked here, newest first.
Sep 2, 2016Certificate of Occupancy
Certificate of Occupancy · 6444751-CN · Construction Permit
Jun 20, 2016Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Jun 20, 2016Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Jun 20, 2016Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Jan 8, 2016Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Dec 23, 2015Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Dec 17, 2015Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Dec 10, 2015Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Nov 5, 2015Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Nov 5, 2015Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Oct 30, 2015Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Sep 24, 2015Special Inspection-Structural
Special Inspection-Structural · 6444751-CN · Construction Permit
Aug 26, 2015Permit
Permit · 6444751-CN · Construction Permit
Aug 26, 2015Cover Sheet
Cover Sheet · 6444751-CN · Construction Permit
Jul 27, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jul 13, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jun 24, 2015Arborist Report
Arborist Report · 6444751-CN · Construction Permit
Jun 24, 2015Calculations-Cooling & Heating
Calculations-Cooling & Heating · 6444751-CN · Construction Permit
Jun 24, 2015Calculations-Cooling & Heating
Calculations-Cooling & Heating · 6444751-CN · Construction Permit
Jun 24, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jun 24, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jun 24, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jun 24, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jun 24, 2015No Protest Agreement
No Protest Agreement · 6444751-CN · Construction Permit
Jun 24, 2015Covenant-Condominium Sale Prohibition
Covenant-Condominium Sale Prohibition · 6444751-CN · Construction Permit
Jun 24, 2015Waste Diversion Plan
Waste Diversion Plan · 6444751-CN · Construction Permit
May 28, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
May 7, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
May 7, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Apr 30, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Apr 14, 2015Arborist Report
Arborist Report · 6444751-CN · Construction Permit
Apr 14, 2015Correction Response
Correction Response · 6444751-CN · Construction Permit
Apr 14, 2015Calculations-Cooling & Heating
Calculations-Cooling & Heating · 6444751-CN · Construction Permit
Apr 14, 2015Calculations-Cooling & Heating
Calculations-Cooling & Heating · 6444751-CN · Construction Permit
Apr 14, 2015No Protest Agreement
No Protest Agreement · 6444751-CN · Construction Permit
Apr 14, 2015Covenant-Condominium Sale Prohibition
Covenant-Condominium Sale Prohibition · 6444751-CN · Construction Permit
Apr 14, 2015Code Modification or Alternate Request
Code Modification or Alternate Request · 6444751-CN · Construction Permit
Apr 14, 2015Correction Response
Correction Response · 6444751-CN · Construction Permit
Feb 18, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Feb 12, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jan 23, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jan 9, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jan 6, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Jan 6, 2015PUBLISHED Decision/Recommendation
PUBLISHED Decision/Recommendation · 6444751-CN · Construction Permit
Jan 2, 2015Correction Letter
Correction Letter · 6444751-CN · Construction Permit
Dec 11, 2014Intake Transmittal
Intake Transmittal · 6444751-CN · Construction Permit
Dec 11, 2014Owner/Agent Authorization
Owner/Agent Authorization · 6444751-CN · Construction Permit
Dec 10, 2014Coversheet
Coversheet · 6444751-CN · Construction Permit
Dec 10, 2014Contractor Disclosure
Contractor Disclosure · 6444751-CN · Construction Permit
Dec 10, 2014Application Materials-General
Application Materials-General · 6444751-CN · Construction Permit
Dec 10, 2014Heating Equipment Sizing Form
Heating Equipment Sizing Form · 6444751-CN · Construction Permit
Dec 10, 2014Financial Responsibility
Financial Responsibility · 6444751-CN · Construction Permit
Nov 5, 2014Site Plan
Site Plan · 6444751-CN · Construction Permit