10608 NE 2nd St
Data updated November 27, 2026, 4:50 PM PT
Neighborhood: Downtown Bellevue
- Latest activityFeb 28, 2020
About this project
Soma Towers Phase 2 at 10608 NE 2nd St in Downtown Bellevue is a 19-story building with 127 apartments over 3 levels of commercial space and an amenity level, with 4 levels of parking below. The tower connects to the project's first phase at the parking, commercial, and amenity floors. Its construction permit (13 130491 BB) was filed in September 2013, supported by clearing and grading (13 130511 GD) and shoring (14 109497 BV) permits.
Latest activity
Feb 28, 2020 update
The last permit movement was the clearing and grading permit (13 130511 GD) closing in February 2020, well after the building itself. The project was completed in August 2017, when the Phase 2 construction permit (13 130491 BB) closed.
Timeline
- ProposedSep 30, 2013
- Construction startedSep 9, 2014
- CompletedAug 30, 2017