About this project

Soma Towers Phase 2 at 10608 NE 2nd St in Downtown Bellevue is a 19-story building with 127 apartments over 3 levels of commercial space and an amenity level, with 4 levels of parking below. The tower connects to the project's first phase at the parking, commercial, and amenity floors. Its construction permit (13 130491 BB) was filed in September 2013, supported by clearing and grading (13 130511 GD) and shoring (14 109497 BV) permits.

Latest activity

Feb 28, 2020 update

The last permit movement was the clearing and grading permit (13 130511 GD) closing in February 2020, well after the building itself. The project was completed in August 2017, when the Phase 2 construction permit (13 130491 BB) closed.

Timeline

Permits

13 130491 BBMajor Commercial Project Closed
Soma Towers Phase 2 consists of a 203,677 GSF 19 storied building, with 4 levels of parking (P4 to P1), three levels of commercial spaces (Level 1, 1A & 2), one level of tenant amenity programs (Level 3), and 15 levels of residential units (Level 5-21). The tower is designed to connect with the first phase of the project at the parking, commercial and amenity floors.
13 130511 GDClearing & GradingExpired
Clear & grade for the preparation of the area for construction of mixed use development.
14 109497 BVShoring PermitClosed
Shoring work for Phase 2 of project., 13130491
15 102886 BBMajor Commercial Project Canceled
Install 456 devices to fire alarm system. This Folder was Cancelled during the Automatic Add phase.

Documents