10961 NE 2nd Pl
Data updated November 27, 2026, 4:50 PM PT
Neighborhood: Downtown Bellevue
Completed
About this project
At 10961 NE 2nd Pl in Downtown Bellevue, an 8-story apartment building with 154 units and live-work commercial units at grade stands over 3 levels of sub-grade structured parking. The design review (15 103556 LD) was filed in January 2015 and issued in February 2016. Construction was split between a subterranean garage permit (15 115337 BB) and the residential building permit (15 115339 BB), with a soil-nailed shoring permit (15 115343 BV) supporting the excavation.
Latest activity
Jan 11, 2019 update
The grading, garage, and building permits (15 111821 GD, 15 115337 BB, and 15 115339 BB) all closed in January 2019, the project's completion date. No later filings appear in the record.
Timeline
- ProposedJan 23, 2015
- Construction startedMar 4, 2016
- CompletedJan 11, 2019
Permits
Proposed 8 level residential construction (live-work commercial units at grade) over 3 levels of sub-grade structured parking. Construction type for this mid-rise project will be IB.
Clearing and grading of a 26,662sf site for a 3-level subterranean parking garage with an 8-story multifamily residential tower including ROW frontage improvements on the north and south property frontages.
Construction of a new subterranean parking garage.
8 story residential multi-family apartment building.
Temporary soil nailed shoring system.
IN ORDER TO OFFER FAILURE RESISTANT GIGABIT SERVICE TO THE TENANTS OF THE EVERGREEN PLAZA APARTMENTS: PLACE (2) MICROWAVE RADIO ANTENNAS LOWER ROOF DECK AT EAST END OF ROOFTOP. PAINT ALL ROOFTOP RADIO EQUIPMENT, MASTS, CONDUIT & JUNCTION BOXES TO MATCH SURROUNDING BACKGROUND DETAIL TO MINIMIZE VISIBILITY FROM GROUND LEVEL AND FROM ADJACENT BUILDINGS.
Documents
Bellevue does not publish permit documents. Permit records are at