415 106th Ave NE
Data updated November 27, 2026, 4:50 PM PT
Neighborhood: Downtown Bellevue
- Stories16
- Latest activityFeb 7, 2017
About this project
Centre 425, at 415 106th Ave NE in downtown Bellevue, is a 16-story office building with retail and a branch bank at ground level, common spaces and a fitness center on the 2nd level, and office space from level 3 to 16, over an 8-level underground parking garage. A preapplication conference in November 2012 (12 127823 DB) opened the project and a design review (14 124031 LD) followed in 2014. Construction was phased, the garage first (14 141077 BB) and the tower above it second (14 147930 BB).
Latest activity
Feb 7, 2017 update
The building was completed in February 2017, when both the garage permit (14 141077 BB) and the tower permit (14 147930 BB) closed. Excavation and grading (14 133099 GD) had closed days earlier, and no filings in the family postdate completion.
Timeline
- ProposedNov 1, 2012
- Construction startedDec 3, 2014
- CompletedFeb 7, 2017