The counted project at 450 110th Ave NE in downtown Bellevue, the Bellevue City Hall address, is a 4-story addition to the existing 4-story east parking garage, adding 138 parking spaces to offset parking lost to another project on the site. The addition was filed in May 2014 as a building permit (14 132965 BB) with a grading permit alongside, and a land use exemption (14 134549 LJ) recorded the parking count. The wider permit family filed under this address includes many citywide public works permits.
Temporary concrete pad for 2 sculptures.
Repair broken and heaved sidewalk panels and replace ADA ramps on corners adjacent to 2011 overlay streets. There are multiple sites for this permit.
Install artwork for temporary sculpture exhibition.
Programatic clear and grade for vegetation management in critical areas.
Install concrete pad/pedestal in existing concrete planter at main plaza of City Hall to install new Fu Dog Sculpture.
WABO approved special inspection agency is required for installation of 8 epoxy anchors.
Roadway repair and resurfacing in various locations citywide.
Removing cement concrete curb and gutter, removing cement concrete sidewalk, removing asphalt pavement, removing pavement marking, erosion control, traffic control, constructing cement concrete curb and gutter, constructing cement concrete sidewalk, grind and overlay, hot mix asphalt paving, bioswale construction, constructing cement concrete curb ramps, pavement marking/channelization, permanent signing, property restoration and other miscellaneous work.
Construct new 4-story addition to existing 4-story parking garage.
Construction of four tier addition to existing four tier open parking garage. Re-grade driveway and relocate dwer and storm drain.
Temporary art installation.
This project proposes to add 138 new parking spaces to the existing 4-story east parking garage to partially offset the loss of parking in the north garage to be caused by another project on the site.
Repair and replace curb, gutter and sidewalk ramps to be ADA compliant at intersections adjacent to 2015 Overlay Program roadway resurfacing and repair sites.
The 2015 Overlay Program will grind and overlay several streets requiring this maintenance. This portion of the project is exempt from requiring a CG permit.Work that will be included in the 2015 Overlay Program that requires a clear a grade permit includes sidewalk repair, median island construction, pavement repair including subgrade andmidblock crossing construction.
This project will remove the existing sidewalk on the west side of Bellevue Way NE, south of NE 24th Street, where the sidewalk does not have a landscape buffer. A retaining wall will be constructed near the ROW line and the Sidewalk and fence will be constructed, giving a landscape buffer at this location. This project also constructs a new S/W on NE 24th Street, between 103rd Ave NE and Bellevue Way NE.
Approx 2,000 sf of temp shoring for building excavation.
Install an extensive green roof assembly on the 3rd floor roof. An irrigation system will also be installed. Includes clear & grade. Incl LUX
This project combines the ADA curb ramp retrofit and pavement grinding and overlay along the 2016 Overlay candidate sites.
Downtown side urban design improvements and interim upgrades.
The proposal consists of installing two (2) microwave dishes and associated equipment to an existing communications facility on the roof of Bellevue City Hall and one (1) new battery rack in the 7th floor equipment room to effectively transmit and receive emergency radio communications., App. ID# 398209
The proposal consists of installing two (2) microwave dishes and associated equipment to an existing communications facility on the roof of Bellevue City Hall and one (1) new battery rack in the 7th floor equipment room to effectively transmit and receive emergency radio communications., 17-104148-CD
Roadway resurfacing and ADA sidewalk improvements
Install replacement fire hydrant assemblies to standardize hydrants across the system. This will require replacing portions of ductile iron water mains, water services and water system appurtenances, removing the existing hydrants, and abandon in place the laterals that served these hydrants.
Install a mural on the temporary wall outside the second floor entrance to City Hall. Wall limits access to light rail construction.
Install replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place most of the existing AC water main, in the right-of-way on SE 8th St., between 143rd Pl SE & 148th Ave SE. The Work includes excavation of approximately 800 cubic yards (bank) and the placement of 700 yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation.
Install replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main within the right of way on SE 8th St., between 143rd Pl SE & 148th Ave SE. The Work includes excavation of approximately 850 total cubic yards (bank) and the placement of 760 total cubic yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation.
Provide shoring for providing earth retention for construction of the Bellevue Downtown Station tunnel. Use of soldier piles and lagging for shoring.
Installation of handrail to NW landscape monumental stair.
Designate ADA smoking area. Remove soil appx 3 yards- install riser on drain-5/8 crushed rock and paver base , compact and install pavers Cover area w/ triangular tensioned fabric panel- utilize existing structure to attach two points of triangular panel and install 1ea new 3" steel post to capture 3rd point
Install replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place most of the existing AC water main, in the right-of-way on NE 36TH ST., NE 37TH ST., NE 39TH ST., 122ND AVE. NE, NE 24TH ST., NE 25TH ST., NE 26TH ST., NE 26TH PL., NE 28TH ST., 107TH AVE. NE, 108TH AVE. NE, 109TH PL. NE, 110TH AVE. NE, NE BELLEVUE REDMOND RD., 115TH AVE. NE (CUL-DE-SAC), and SE 40TH ST. The Work includes excavation of approximately 6,700 cubic yards (bank) and the placement of 6,600 cubic yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation.
Replacement and abandonment of existing AC water main with new ductile iron water main and HDPE water main. Replacement and potential abandonment of existing AC sanitary sewer force main with new HDPE sanitary sewer force main. Horizontal directional drill will be utilized to install portions of HDPE sanitary sewer force main and water main in forested areas. The work also includes installing new fire hydrants, replacing existing water services, traffic control, and other work as required on private property. Parcels included: 885710TR-C, 885720trct, 885730TR-C, 885731TRC6, 885731TRCT, 3986900000, 3986500010, 1099100529, 3525059029, 3316500185, 3316500210, 3316500225, 3316500230, 3316500235, 3316500265, 3316500270, 3316500275, 3316500315, 3316500340
Install replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main.
AC water main replacement at sites E, G, H (120th Ave NE, SE 30th St/106th Ave SE, Lake Hills Blvd, and 148th Ave SE).
Install replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main. The Work includes excavation of approximately 6,010 cubic yards (bank) and the placement of 5,910 yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation., NA
Decommission of existing pond water feature and installation of planting area and deck.
Lot north of City Hall, between
CH building and sound Transit light rail for use as a temporary long term off-leash dog facility maintained by Bellevue Parks.
The purpose of this project is to maintain the existing roadway infrastructure by resurfacing the roadways and replacing the existing sidewalk and ADA curb ramps for the Downtown NHS Overlay project. Curb, gutter, and sidewalk will be replaced as necessary for maintenance to reduce trip hazards. The ADA curb ramps will be replaced to meet current ADA requirements. All work performed on this contract will be contained within the existing impervious surfaces in the roadway prism. This project does not add any new impervious areas.
Install replacement ductile iron and high-density polyethylene water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main. The Work includes excavation of approximately 4,700 cubic yards (bank) and the placement of 4,600 yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation., 22-10784.00
Install temporary structure to cover Fire Engine 10 so it will be out of the elements during the inclement weather season., 23-111374 LR
Install replacement ductile iron and high-density polyethylene water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main. The Work includes excavation of approximately 8,800 cubic yards (bank) and the placement of 8,700 yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation., 22-10784.00
The City of Bellevue will be installing approximately 10,370 linear feet of replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main. This is a multi-site project including 2 sites in Medina for a total of 15,640 LF of AC water main replacement. The Work in Bellevue includes excavation of approximately 5,400 cubic yards (bank) and the placement of 5,400 cubic yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation.
The work consists of grind and overlay of existing pavement, channelization, and curb ramp installation. Other work consists of installing loops, pushbuttons, pole, raised crosswalk, and speed humps.
The City of Bellevue will be installing approximately 12,362 linear feet of replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main. This is a multi-site project including 1 site in Clyde Hill for a total of 14,230 LF of AC water main replacement. The Work in Bellevue includes excavation of approximately 5,200 cubic yards (bank) and the placement of 5,200 cubic yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation.
The City of Bellevue will be installing approximately 11,030 linear feet of replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main. This is a multi-site project for a total of 11,030 LF of AC water main replacement. The Work in Bellevue includes excavation of approximately 6,000 cubic yards (bank) and the placement of 5,900 cubic yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation.
We're installing RRFBs & crosswalks in these areas:
Lakemont Blvd SE & SE 58th St
165th Ave SE & SE 46th St
SE 46th St & 167th Ave SE
The project will require the installation of up to 21 sidewalk sticker decals (all 3 feet in diameter, or 7 square feet) and four aluminum signs ranging from 3 square feet for the smallest sign and the larger signs at 22 and 87 square feet in prominent locations). These stickers and signs are strategically proposed throughout the 1.5-mile corridor in high visibility and high foot traffic areas to maximize public engagement., 25 104004 DC
The City of Bellevue will be installing approximately 2,720 linear feet of replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place of the existing AC water main. The Work includes excavation of approximately 1,400 cubic yards (bank) and the placement of 1,300 cubic yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets will be kept clean during construction. A street sweeper will be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation. Work is predominantly within the public right of way or along private roadways with some watermain installation across developed landscape on private property.
The City of Bellevue will be installing approximately 10,100 linear feet of replacement ductile iron water mains, fire hydrants, water services and water system appurtenances and abandon in place the existing AC water main. The Work includes excavation of approximately 5,600 cubic yards (bank) and the placement of 5,600 cubic yards (bank) of new trench backfill (mostly crushed rock and asphalt). Streets to be kept clean during construction. Street sweeper to be used as needed. It is expected that excavated material will be removed from the construction sites during the initial excavation. Any excavated materials that are to be kept on sites more than 48 hours by the contractor will be covered. All downstream catch basins will be fitted with sediment inserts prior to beginning excavation. The 10,100 linear feet includes approximately 7,090 linear feet in City of Bellevue, 1,210 linear feet in City of Clyde Hill, and 1,800 linear feet in City of Medina. Similarly, approximate excavation quantities are 3,930 cubic yards in City of Bellevue, 670 cubic yards in City of Clyde Hill and 1,000 cubic yards in City of Medina.