Two office towers, one 12 stories and one 13 stories totaling 800,000 sq. ft., with 4,000 sq. ft. of street-level retail, stand at 300 Boren Ave N in Seattle's South Lake Union; the project was first filed in August 2011. Parking for up to 1,120 vehicles sits below grade on a shared podium, and the facades of the two existing structures on the site were retained through demolition. The Master Use Permit (3012675-LU) was issued in November 2013.

Latest activity

Jan 12, 2018 update

The towers completed in September 2017, when Certificates of Occupancy were issued for the phased permits 6361888-PH, covering the podium and south tower, and 6367484-PH, covering the north tower. Tenant alteration permits for Amazon followed into January 2018 (6578134-BK). The file holds 930 special-inspection reports, the most recent in March 2017.

Timeline

Permits

3012675-LUMaster UseIssued
Land Use Application to allow two office towers (one, 12-story and one, 13-story, 800,000 sq. ft.) with 4,000 sq. ft. of retail at street level. Parking for up to 1,120 vehicles will be provided below grade. Review includes demolition of 85,000 sq. ft. of existing structures. The facades of the two existing structures to remain.
6361888-PHPhasedCompleted
Construction of base podium and south tower of office and retail building with below grade parking and occupy per plan. The facades of the two existing structures to remain.
6367484-PHPhasedCompleted
Construction of north office tower of office and retail building with below grade parking and occupy per plan. The facades of the two existing structures to remain.
6367485-CNConstructionCompleted
Shoring and excavation for construction of podium north and south towers of office and retail building on common podium with below grade parking per plan
3012675-EGEarly Design GuidanceCompleted
Early Design Guidance for: Land Use Application to allow two office towers (one, 12-story and one, 13-story, 800,000 sq. ft.) with 4,000 sq. ft. of retail at street level. Parking for up to 1,120 vehicles will be provided below grade. Review includes demolition of 85,000 sq. ft. of existing structures. The facades of the two existing structures to remain.
6380479-DMDemolitionCompleted
Demolish existing commercial landmark building "Troy Laundry Building" (facade to remain) per plan
6380480-DMDemolitionCompleted
Demolish existing commercial landmark building "Boren Investment Building" (facade to remain) per plan
6524429-BKBlanket TIActive
Blanket Permit for interior non-structural alterations. Administrative permit only - no work authorized.
6526897-BKBlanket TICompleted
Blanket Permit for interior non-structural alterations for tenant Amazon. FLOORS 3-13
6578134-BKBlanket TICompleted
Blanket Permit for interior non-structural alterations to the 3rd floor. For AMAZON per plans.

Documents

60 documents tracked here, newest first, of 1,104 on file with the city.
Apr 28, 2018Preliminary Assessment Report
Preliminary Assessment Report · 3012675-LU · Master Use Permit
Sep 5, 2017Certificate of Occupancy
Certificate of Occupancy · 6361888-PH · Phased Project Permit
Sep 5, 2017Certificate of Occupancy
Certificate of Occupancy · 6367484-PH · Phased Project Permit
Jun 21, 2017Certificate of Occupancy
Certificate of Occupancy · 6367484-PH · Phased Project Permit
Apr 13, 2017Side Sewer Permit
Side Sewer Permit · 6361888-PH · Phased Project Permit
Apr 3, 2017Certificate of Occupancy
Certificate of Occupancy · 6367484-PH · Phased Project Permit
Mar 27, 2017Special Inspection-Structural Final Report
Special Inspection-Structural Final Report · 6367484-PH · Phased Project Permit
Mar 17, 2017Special Inspection-Geotechnical Final Report
Special Inspection-Geotechnical Final Report · 6367485-CN · Construction Permit
Mar 15, 2017Special Inspection-Structural Final Report
Special Inspection-Structural Final Report · 6367484-PH · Phased Project Permit
Mar 2, 2017Financial Responsibility
Financial Responsibility · 3012675-LU · Master Use Permit
Jan 24, 2017Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jan 20, 2017Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jan 19, 2017Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Nov 15, 2016Design Review Proposal
Design Review Proposal · 3012675-LU · Master Use Permit
Sep 19, 2016Special Inspection-Structural Final Report
Special Inspection-Structural Final Report · 6361888-PH · Phased Project Permit
Sep 15, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Sep 15, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Sep 13, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Sep 13, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Sep 9, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Aug 15, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Aug 12, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Aug 12, 2016Certificate of Occupancy
Certificate of Occupancy · 6361888-PH · Phased Project Permit
Aug 11, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Aug 11, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Aug 10, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Aug 5, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Aug 3, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Aug 2, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Aug 2, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Aug 2, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Aug 2, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Aug 2, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Aug 2, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 29, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 29, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 29, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 27, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 27, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 27, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 27, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 27, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 27, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 26, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 26, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 26, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 21, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 21, 2016Special Inspection-Structural
Special Inspection-Structural · 6361888-PH · Phased Project Permit
Jul 18, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 18, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural
Special Inspection-Structural · 6367484-PH · Phased Project Permit
Jul 14, 2016Special Inspection-Structural