Presentation: Design Review Proposal, May 10, 2018. Source: Seattle city records.1 / 12
Stories16
City documents on file1,665
Latest activityMay 8, 2023
About this project
A 16-story office building with street-level retail stands at 400 Westlake Ave N in Seattle's South Lake Union neighborhood, first filed in October 2015. The scheme added 13 stories over the existing 2-story Firestone Auto Supply and Service Building, keeping its west and south facades, with parking for 60 vehicles. Early design guidance (3022779-EG) weighed a 15-story result and a 16-story option under the Living Building Pilot Program. The Master Use Permit (3022779-LU) was issued in October 2019.
Latest activity
May 8, 2023 update
Completion came on May 8, 2023, when a Certificate of Occupancy was issued for the phased construction permit (6716779-PH). Construction began in December 2020, after shoring and excavation (6612960-CN) and demolition that retained the Firestone facades (6615996-DM). The file holds 1,245 special-inspection reports, the most recent in April 2023.
Land Use Application to allow a 13-story addition over an existing 2-story landmark building (Firestone Auto Supply and Service Building) resulting in a 15-story office building with retail. The west and south facades of the existing structure to remain. Parking for 60 vehicles proposed. Project considers an option resulting in a 16-story building relating to the pending 2030/Living Building Pilot Program (LBPP) Ordinance.
Phased project: Construction of mixed use building with below grade parking and occupy per MUP 3022779 and per plans. Landmark facades on west south and portion of east sides of former Firestone structure to be retained
Early Design Guidance for: Land Use Application to allow a 13-story addition over an existing 2-story landmark building (Firestone Auto Supply and Service Building) resulting in a 15-story office building. Retail proposed at street level. The west and south facades of the existing structure to remain. Parking for 67 vehicles proposed. Project considers an option resulting in a 16 story building relating to the pending 2030/Living Building Pilot Program (LBPP) Ordinance.
Shoring and Excavation for construction of mixed use building with below grade parking per MUP 3022779 and per plans. Landmark facades on west south and portion of east sides of former Firestone structure to be retained.
Demolish existing commercial building at 400 Westlake Ave N. Landmark facades on west south and portion of east sides of former Firestone structure to be retained.
Documents
60 documents tracked here, newest first, of 1,665 on file with the city.