4000 15th Ave NE in Seattle's University of Washington neighborhood anchors a long campus permit family, first filed in February 2008. The lead filing proposed a 5-story, 132,800 square foot business school structure, removing 95 surface parking spaces, and its Master Use application (3006631-LU) was issued in October 2008. A separate council land use action (3023261-LU), filed in November 2016, sought adoption of a new Major Institution Master Plan for the campus, with a rezone for modified height limits and potential development of 6,000,000 square feet.
The newest dated construction work is an art installation addition and alteration permit (7071967-CN), issued in June 2025 and completed in October 2025. The campus plan action (3023261-LU) remains at published status, and a chemistry sciences building application (3042974-LU) stands at additional information requested, with no dates in the record.
Land Use Application to allow a 132,800 sq. ft., five-story structure (Business School, University of Washington). Ninety-five surface parking spaces to be removed. Supplemental Environmental Impact Statement prepared by the University of Washington.
Cancelled per applicant request. Land Use Application to allow demolition of an existing 5,300 sq. ft. structure. (Moore Hall Annex)
construct a parking lot for the Plant Services Building with approximately 60 parking stalls.
Council Land Use Action to adopt a new Major Institution Master Plan for the University of Washington Seattle Campus. A rezone is required for a modification to MIO height limits. The proposal includes potential development of six million square feet and street vacations. Environmental Impact Statement has been prepared by the University of Washington.
Early Design Guidance for: Streamlined Design Review application proposing to remove 121 trees (including 14 exceptional trees), for the construction of a new Health Facility on the University of Washington Main Campus.
Streamlined Design Review application proposing to remove 121 trees (including 14 exceptional trees), for the construction of a new Health Facility on the University of Washington Main Campus.
Exceptional tree removal - Construction of new 5-story classroom and office building on the UW Campus
SDR - Exceptional tree removal - Construction of new 5-story classroom and office building on the UW Campus
UW CHEMISTRY SCIENCES BUILDING
Alterations to existing institutional building (UW Hutchison Hall) to change use from pool to design studio and occupy per plan.
Construct access road for the NE 45th street viaduct per plan (City Project)
Construct interior alterations to offices and assembly area 1st floor of existing UW Mary Gates Hall per plan.
Construct altertions to Kane Hall at elevator machine room per plan.
Replace roof waterproofing and flashing relocate several interior and exterior mechanical and ventilation units and install parapet guards all per plans. ( Mechanical Engineering Building)
Construct alterations to lab #291 in Bagley Hall per plan.
Alter existing elevators and penthouse at Kincaid Hall (U of W) per plan.
Construct alterations to existing office Lab space on third floor of Kincaid Hall per plot plan and subject to field inspection STFI.
Construct alterations to elevator shafts of Padelford Hall in UW per plan.
Construct tenant improvements to existing UW Barkley Hall 2nd floor Lab 233 per plan
Tenant improvements to a ground floor office suite at Mary Gates Hall per plan.
Construct alterations to all floors of exsiting Mech. Engineering Building at UW for communication upgrade and construct new closet in existing basement storage area per floor plan and subject to field inspection.
Construct interior non-structural alterations to fourth floor of Guggenheim Hall (U of W) per floor plan and subject to field inspection STFI.
Construct alterations to convert portion of stack area to student organization office and meeting space at the Law Library Mary Gates Hall and occupy per plan.
Alterations to existing institution building to install a carillon on roof of Kane Hall per plan.
Construct generator enclosure at UW campus per plans. (Construct stand alone generator enclosure and alterations to existing classroom buildings. Reviews and processing for 3 A/Ps under 6399650)
Construct interior alterations to teaching labs at second floor of Baley Hall per plans. (Mechanical included)
CLOSED AS INCOMPLETE - EXPIRED PERMIT. Tenant improvements to existing commercial building on 2nd floor - University of Washington's Dean's office Suite 222 Miller Hall Mechanical included per plans.
Construct tenant improvements to basement level of Bloedel Hall U of W per plan.
Alterations to basement of Atmospheric Sciences Building UW per plans. (Construct stand alone generator enclosure and alterations to existing classroom buildings. Reviews and processing for 3 A/Ps under 6399650)
Alterations to basement of Kane Hall UW per plans. (Construct stand alone generator enclosure and alterations to existing classroom buildings. Reviews and processing for 3 A/Ps under 6399650)
Construct tenant improvement to interior of an existing UW building - ground 3rd & 4th floor per plans
Construct alteration to levels 3-4 and roof of existing research lab bldg per plans. (Mechanical included)
CLOSED AS INCOMPLETE - EXPIRED PERMIT. Install anchors on roof of UW building per plans
Alteration to 5th floor for the book and Paper Conservation Lab per plan.
Change of use of portion of library to restaurant and construct tenant improvements to existing Library (UW Suzzallo library) on first floor for Starbucks occupy per plan. mechanical included.
Interior alterations to portion of existing lab on 3rd floor of Bagley Hall at University of Washington per plan.
Construct alterations in classrooms at Lowe Hall (rooms 101 102 105 and 106) at the University Of Washington subject to field inspection (STFI)
Shoring and Excavation for Construction of office and classroom building on the campus of the University of Washington per plan
Construct Voluntary Seismic Upgrades to existing instutional building at University of Washington College (Gowen Hall building 1201) per plan.
Voluntary Seismic Upgrade of Johnson Hall for the University of Washington (1707 NE Grant Lane) per plans.
Construct Voluntary Seismic Upgrades to existing institutional building (Lewis Hall) at University of Washington per plan.
Voluntary Seismic Upgrade of Mary Gates Hall for the University of Washington (1851 NE Grant Lane) per plans.
Construct voluntary seismic upgrades to existing UW Music Building (2034 NE Skagit Lane) per plan.
Construct voluntary seismic upgrade at rooftop of existing institutional structure (Power Plant Building) per plan.
Cosntruct alterations to the Electrical Engineering Bldg (UW) to replace the chillers per plan. Mechanical is included.
Construct alterations to existing Suzzalo Library (UW) at the main floor level room 150 subject to field inspection.
Construct additions and alterations for art installation (UW Denny Lawn) in northeast side of landscape of existing institutional property per plans.